OrthoArkansas

LOCATION
little rock, Arkansas

architect
Cromwell Architects Engineers

Client
OrthoArkansas

 

PROJECT FACTS

  • New 80,351 Square Foot Healthcare Facility

  • Fast Track 12 Month Schedule

  • Kinco Hired: December 2016

  • Conceptual Budget: December 2016

  • DD Budget: January 2017

  • Bid Site Package: January 2017

  • Mobilize & Start Sitework: February 2017

  • Bid Building Core & Shell Pckg: March 2017

  • Start Building Core & Shell: March 2017

  • Bid Finish Trades: April 2017

  • Establish Final GMP: April 2017

  • Building in the Dry: Sept. 2017

  • Substantial Completion: February 2018

SF HEALTHCARE FACILITY