- New 80,351 Square Foot Healthcare Facility
- Fast Track 12 Month Schedule
- Kinco Hired: December 2016
- Conceptual Budget: December 2016
- DD Budget: January 2017
- Bid Site Package: January 2017
- Mobilize & Start Sitework: February 2017
- Bid Building Core & Shell Pckg: March 2017
- Start Building Core & Shell: March 2017
- Bid Finish Trades: April 2017
- Establish Final GMP: April 2017
- Building in the Dry: Sept. 2017
- Substantial Completion: February 2018